NEPRA Hearing: Fuel Charges Adjustment for July 2026 (Ex-WAPDA DISCOs) — 27 Aug 2026
NEPRA Hearing · Islamabad · Jang,
Notice advertisement published in Jang on Tuesday, 18 August 2026, listed under Islamabad, Pakistan. Issued by NEPRA Hearing. The last date printed on the advertisement was Thursday, 27 August 2026 and has passed.
The original image is temporarily unavailable. Use the source link or the details below. Open the full-size clipping Advertisement details
Issuer: National Electric Power Regulatory Authority (NEPRA). Purpose: Public hearing on the fuel charges adjustment (FCA) requested by Central Power Purchasing Agency – Guarantee Limited (CPPA-G) for the month of July 2026 affecting ex-WAPDA distribution companies (to be applied also to K-Electric consumers as per policy guidance).
CPPA-G has submitted detailed generation, fuel cost and unit rate data for July 2026 and requested an increase of Rs. 2.52/kWh over the reference fuel charge, yielding a requested FCA reference of Rs. 7.0929/kWh for July 2026. Interested and affected parties may raise written/oral objections at the hearing as permissible under law. Relevant filings, Act, rules, regulations, codes and Authority determinations requested/ filed by CPPA-G are available on NEPRA's website: www.nepra.org.pk.
| Generation Source | GWh | % Share | Million Rs | Rs/kWh |
|---|---|---|---|---|
| Hydel | 6,019 | 39.81% | – | – |
| Coal - Local | 1,650 | 10.91% | 17,184 | 10.4174 |
| Coal - Imported | 2,169 | 14.34% | 35,427 | 16.3348 |
| HSD | 31 | 0.21% | 1,694 | 54.4796 |
| RFO | 215 | 1.42% | 10,773 | 50.0776 |
| Gas | 990 | 6.54% | 13,629 | 13.7717 |
| RLNG | 1,629 | 10.78% | 77,198 | 47.3798 |
| Nuclear | 1,527 | 10.10% | 4,626 | 3.0299 |
| Import (Iran) | 58 | 0.38% | 1,519 | 26.2813 |
| Wind | 682 | 4.51% | – | – |
| Bagasse | 429 | 2.83% | 499 | 10.8821 |
| Solar | 106 | 0.70% | – | – |
| Energy Generated (Total) | 15,122 | 100% | 162,549 | 10.7495 |
| Previous Adjustment | – | – | (21,720) | (1.4363) |
| Sale to IPPs | (26) | (0.17%) | (1,459) | 55.4119 |
| Transmission Losses | (594) | (3.93%) | – | 0.3784 |
| Net Delivered to DISCOs | 14,501 | 95.90% | 139,370 | 9.6112 |
Hearing details:
Date & Time: 2026-08-27 (Thursday) at 2:00 PM
Venue: NEPRA Tower (Attaturk Avenue East, G-5/1), Islamabad and Online. Zoom participation link published by NEPRA: https://us02web.zoom.us/j/86506963055
Contact / Filing information:
Registrar NEPRA: Wasim Anwar Bhinder
NEPRA Tower, Attaturk Avenue (East), G-5/1, Islamabad
Phone: 051-2013200 | Fax: 051-2600021
Email: [email protected]
Website: www.nepra.org.pk