· Pakistan’s newspaper advertisement archive
DailyAds.pk
Saved
Notices Closed 25 Sep 2026

NEPRA Hearing Notice — Tariff Modification Petition by SK Hydro for 884 MW Sukhi Kinari Hydropower Project

NEPRA Hearing Notice · Islamabad · Dunya,

Notice advertisement published in Dunya on Thursday, 10 September 2026, listed under Islamabad. Issued by NEPRA Hearing Notice. The last date printed on the advertisement was Friday, 25 September 2026 and has passed.

Similar notices

All notices

Advertisement details

Issuer: National Electric Power Regulatory Authority (NEPRA)

Notice type: Notice of Admission / Hearing — Petition for modification of tariff filed by SK Hydro (Pvt) Ltd for 884 MW Sukhi Kinari Hydropower Project.

Petitioner: SK Hydro (Pvt) Ltd

Project: Sukhi Kinari Hydropower Project (884 MW)

Summary of requested modifications and additional costs:

Description Cost (USD millions) Cost (PKR)
Revised EPC Cost (design change net reduction) (USD 28.6 million plus additional USD 28.99 million on account of diversion of N-15 Highway) 1285.692 -
Shunt Reactors Cost (including NESPAK Consultancy fee of PKR 74.24 millions) 11.372 915.180
Security Infrastructure - construction period - 918.635
Covid-19 Anti Epidemic Cost - 30.000
Acceleration - Civil Works - 15.500
Acceleration - Mechanical and Electrical Installation - 2.820
Acceleration - Wet Testing of complex 1.742 243.672

Other reliefs requested:

  • Requested replacement of obsolete PIOC indices with PBS Abbatabad indices and replacement of other input element which are now not published by PBS for indexation of Civil Works.
  • Requested for the adoption of 360 day year convention for interest calculations instead of 365 days.
  • Requested Rs 1,945.964 million for the operation period security infrastructure and Rs 39.964 million for NESPAK consultancy.
  • Requested to allow adjustment of following costs on actual basis at the time of CIOD: IOC, KEO, IIEC, Project Development/Management cost, Project Supervision/Owner's Engineer cost, Law Service Cost, Provincial Sale Tax on Services, Custom duty and Sindh Infrastructure Cess charges.
  • Requested to allow insurance cap of 7% to the insured amount i.e. principal plus interest during construction instead of 7% on total assessed debt.
  • Requested to modify the reference tariff to reflect the increase in the water use charges from Rs. 0.15/kWh to Rs. 0.425/kWh.
  • Adjustment of Contract Capacity of 861.548 MW to 875.160 MW.

Hearing date and time: 01.10.2020 at 02:00 PM

Venue / Virtual access: NEPRA Head Office, Islamabad. Zoom: https://us02web.zoom.us/j/82064467592. Meeting ID: 820 6446 7592

Participation / Filing of interventions and comments:

  • Any interested person who desires to participate in the proceedings may file an intervention request within seven (7) days from the date of publication of this notice.
  • Such intervention request shall state the name and address of the person filing the same, subject and manner in which such person is or is likely to be substantially and specifically affected by any determination in the proceedings.
  • Comments on the matter may also be submitted within seven (7) days of publication of this Notice. The Authority may, at its discretion, consider such comments and interventions in the final determination.

Contact / Filing address:

Registrar NEPRA, NEPRA Tower, Ataturk Avenue (East) G-5/1, Islamabad.

Phone: 051-2013200; Fax: 051-2600021.

Email: registrar@nepra.org.pk

Registrar (printed): Wasim Anwar Bhinder, Registrar NEPRA

List of issues and copy of petition may be downloaded from NEPRA's website: www.nepra.org.pk

(PID) 2321/26

Published in Dunya on Thursday, 10 September 2026. DailyAds.pk indexes newspaper advertisements; the original notice and the issuing organisation remain the source for final terms and eligibility.

Links printed in the advertisement

Also in Dunya · 10 Sep 2026

See all ads
Dunya · 10 Sep 2026
Fit