MEPCO Corrigendum: Amendment No.1 to Tender PK-MEPCO-555004-GO-RFB for Supply of Spun PCC Poles

MEPCO Corrigendum · Multan · Express,

Tender advertisement published in Express on Wednesday, 5 August 2026, listed under Multan. Issued by MEPCO Corrigendum.

Newspaper clipping: MEPCO Corrigendum: Amendment No.1 to Tender PK-MEPCO-555004-GO-RFB for Supply of Spun PCC Poles, Express, 05 Aug 2026 Open the full-size clipping
Original clipping · Express · 05 Aug 2026 · tap to zoom

Advertisement details

Issuer: Multan Electric Power Company Limited (MEPCO). This corrigendum (Amendment No.1) applies to MEPCO Tender No. PK-MEPCO-555004-GO-RFB for supply of HT/LT spun PCC poles for rehabilitation of 11kV feeders (lot-wise). Reference tender notice published on 2026-07-10 under PID (L) 67/26. PID(L)293/26 is shown on this corrigendum.

Amendment Section / Clause Summary of Revision
1 Section II – BDS, ITB 14.8(a)(iii) Delivery revised to EX Works basis. Supplier remains solely responsible for security, custody, surveillance and protection of purchased HT/LT spun poles until collected from supplier premises.
2 Section IV – Price Schedule Column No.7 in the Price Schedule for Lot 1, Lot 2, Lot 3, Lot 4 and Lot 5 revised to read: "Not Applicable."
2 Section VII – Schedule of Requirement Final destination (project site) as specified in BDS revised to: "on EXWorks basis."
3 Section IX – Special Conditions, GCC 18.1 Performance security is required and shall be equal to 05% of the total contract price.
4 Section IX – Special Conditions, GCC 16.1 (ii) On delivery: 80% of the Total EX Works Contract Price, or pro-rata EX Works Contract Price for the quantity delivered on EX Works basis and accepted by the Purchaser, shall be paid upon submission of documents specified in GCC Clause 13.

All other terms and conditions of the bidding document remain unchanged. Issued by: Chief Engineer (Development), PMU MEPCO Multan.

Published in Express on Wednesday, 5 August 2026. DailyAds.pk indexes newspaper advertisements; the original notice and the issuing organisation remain the source for final terms and eligibility.