Tender: AOM&R of All Metaled Roads in District D.I. Khan — C&W Highway Division (e-Procurement)
Tender advertisement published in Daily Mashriq on Monday, 27 July 2026, listed under D.I. Khan. The last date printed on the advertisement was Monday, 10 August 2026 and has passed.
Similar tenders
All tendersMore tenders
Advertisement details
Government of Khyber Pakhtunkhwa, Communication & Works Department, C&W Highway Division D.I. Khan invites electronic bids (Single Stage Single Envelope E-PAD system) from eligible firms/contractors in accordance with KPPRA Procurement Rules for the works listed below. Bidding documents and instructions can be obtained from the office of the undersigned or via the E-PADS system on working days prior to the submission deadline. Bidders must submit e-bids in accordance with the cited KPPRA e-bidding notification and through the E-PADS portal.
| Lot | Name of work | Required Category of PEC | Required Bid Security | Period of Completion | Last date & time for e-Bid submission | Date & time of opening of Financial Bid |
|---|---|---|---|---|---|---|
| 1 | AOM&R of All Metaled Roads in District D.I. Khan for the year 2026-27 | C-6 | 0.210 (as per KPPRA order) | As per Work Order | 2026-08-10 12:00 PM | 2026-08-10 12:30 PM |
Important notes:
- Bid solicitation documents and instructions to bidders can be obtained from the office of the undersigned or E-PADS System on any working day before the submission date.
- The bidders should submit their e-bids as per KPPRA Notification No. SOR (14) / Vol: I-24 / 2021-22/9657 dated 10-05-2022.
- The contractors quoting their bids up to a limit of 10% below Engineer's Estimate shall submit the bid security @ 2% only of Engineer's Estimate.
- Contractors quoting their bids more than 10% below but up to 20% below on Engineer's Estimate shall submit additional security with their bids @8% Additional Security of Engineer's Estimated Cost in addition to 2% bid security. If the bid is not accompanied with the required additional security then it will be considered as non-responsive and the 2% bid security shall be forfeited in favour of Government and the second lowest bidder and so on will be considered according to rule.
- Similarly, a contractor quoting bid more than 20% below shall submit his bid on an additional secured security in Engineer's Estimated Cost equal to the differential amount of submitted bid and Engineer's Estimate alongwith detailed rate analysis. In case of more than 20% below bids, if the bid is not accompanied by the detailed rate analysis and/or required amount of additional security, then the said bid shall be considered as non-responsive. All the securities submitted alongwith such non-responsive bid shall be forfeited in favour of Government and the second lowest bidder and so on will be considered accordingly.
- In case detailed rate analysis submitted with the bids is in view of the Procuring Entity, not convincing, the head of the Procuring Entity may declare such bid as non-responsive without any further notice to such bidders and record reasons thereof.
- The Procuring Entity may offer the contract to next lowest bidder after due diligence in the event that the Contractor withdraws from the contract so which would be may adversely affect procurement opportunity after award of contract.
- After communication of work by the successful bidder, the procuring entity may replace the Additional Security with a bank guarantee of the same amount from the scheduled bank if already deposited security is in the form of cash guarantee.
- The Additional Security shall be released to the contractor in four instalments i.e. 1st instalment 25% to be released upon completion of 25% of the project, 2nd instalment of 25% to be released upon completion of 50% of the project, 3rd instalment of 25% to be released upon completion of 75% of the project and the 4th instalment of 25% to be released after 100% completion of the project. Complete Detail of Bid Security in shape of CDR (i.e. Bank Name, CDR Number(s) and Date(s)) must be uploaded electronically on the E-PADS System and also physically submitted to the office of the undersigned before tender closing time.
- A separate CDR on account of Stamp Duty shall be submitted alongwith the tender documents at the time of tender opening.
- All bidders are required to register with Khyber Pakhtunkhwa Revenue Authority under Finance Act, 2023 NA XXXL of 2023.
- As per KPPRA Notification No. SRO (29) / Vol: I-40 / 25-26, dated 29-10-2025, the additional security, in case of bids more than 20% below, shall be released in instalments as detailed above after award of contract and submission of bank guarantee and subject to completion of the work as per clause.
Issuing office & contact: Executive Engineer, C&W Highway Division, D.I. Khan. Phone: 0966-920558.
Published in Daily Mashriq on Monday, 27 July 2026. DailyAds.pk indexes newspaper advertisements; the original notice and the issuing organisation remain the source for final terms and eligibility.