Addendum No.2 — BWSPIP Bidding Documents for RFB PK-BID-PIU-529995 & PK-BID-PIU-529990
Addendum No.2 · Quetta · Jang,
Tender advertisement published in Jang on Wednesday, 2 September 2026, listed under Quetta, Pakistan. Issued by Addendum No.2. The last date printed on the advertisement was Thursday, 3 September 2026 and has passed.
The original image is temporarily unavailable. Use the source link or the details below. Open the full-size clipping Advertisement details
Issuer: Project Director, Balochistan Water Security and Productivity Improvement Project (Component-A), Jinnah Town, Samungli Road, Quetta. This addendum (No.2 / corrigendum) amends the Bidding Documents for two construction packages and must be acknowledged and incorporated by all prospective bidders.
| RFB No. | Work | Location |
|---|---|---|
| PK-BID-PIU-529995-CW-RFB | Construction of Flood Dispersal / Concrete Weir and Allied Structure | Bohra Wah on Talli River Basin |
| PK-BID-PIU-529990-CW-RFB | Construction of Flood Dispersal / Concrete Weir and Allied Structures | Qaisar Wah on Talli River |
The amendment revises the acceptable ranges of weightages in Section IV - Bidding Forms, "Schedule of Adjustment Data" as follows:
| Description | Unit | Existing Weightage | Revised Weightage |
|---|---|---|---|
| High Speed Diesel (for all types of fuel) | Litre | 0.10 - 0.15 | 0.10 - 0.20 |
| Cement (Ordinary Portland Cement) (for all types of Cement) | Per Bag | 0.10 - 0.15 | 0.10 - 0.20 |
All other entries of the Schedule of Adjustment Data remain unchanged, including Fixed Portion (0.35), Labour Unskilled (0.05-0.10) and Iron Bar (M.S. Bar) 60 Psi (0.10 - 0.20), together with their applicable indices and notes. The weightages proposed by the bidder shall total 1.000. All other terms, conditions, specifications and contents of the Bidding Documents remain unchanged.
Submission deadline: 2026-09-03 at 11:30 AM. Bids will be opened on the same date at 12:00 Noon in the presence of bidders' representatives who choose to attend.
Contact / Submission address: Project Director, Balochistan Water Security and Productivity Improvement Project (Component-A), 117/41-A/1, Jinnah Town, Samungli Road, Quetta. Tel: 081-2503599. Email: [email protected]. Website: www.dprgob.pk.
Published in Jang on Wednesday, 2 September 2026. DailyAds.pk indexes newspaper advertisements; the original notice and the issuing organisation remain the source for final terms and eligibility.